Pre-Delivery Software Testing (Uncontrolled)
A review is required for uncontrolled testing of the software in an equivalent environment to ISS to discover any anomalies before official delivery.
# |
Task |
Nominal Timeline |
Responsibility |
Notes |
||
---|---|---|---|---|---|---|
ROI Exp Team |
ROI SW Team |
PI |
||||
1 |
For SSC software: Contact the SSC Lab for a machine account and path info for the ls1 server. |
|
|
|
✔ |
PI/Developer to setup an account. Requires NDC access. |
2 |
Perform test per Test Plan to verify functionality of software and prove requirements are met. |
|
(✔) |
|
✔ |
Likely use test plan completed as part of JPR requirements. This verification will be included in the delivery to ROI. |
3 |
For HRF load, can be provided a laptop for testing. |
|
(✔) |
(✔) |
✔ |
|
4 |
EST to also perform SVT like operational testing and out of bounds/stress testing and procedure verification, if applicable. |
|
✔ |
(✔) |
(✔) |
Building 241 has a flight-like environment if SSC lab testing schedule is full. If need to add steps to official test plan, include with delivery. |
✔ - Primary Responsibility, (✔) - Secondary Responsibility (assists Primary) |